Skip to Content
avatar image
Former Member

Gap between produce phase and Good Receipt

I encountered a strange issue recently on PPDS planning board, the order's produce activity span 7-8 days but there is a gap of 12-15 days between produce and Goods receipt dates.

Goods receipt processing time is 1 day in Location product master

For ex - produce activity -> 1-Jul to 7-Jul

Goods Receipt -> 20-Jul to 21-Jul

What could cause such issues? User apparently had not done anything unusual recently.

I tried to create orders manually on the planning board, but couldn't reproduce the issue.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers