May 15, 2007 at 12:28 PM

Lot Sizing for Short/Long Term

155 Views

Hello All,

I tried the lot sizing with the short term/Longterm pattern..

But I'm facing the following problem..

I have maintained periodic lot sizing according to the planning calendar(Weeks from Saturday to Friday) for the first month...( Requirement date = period end)

And for the other 2 years I have defined periodic lot sizing with Monthly lot size ( Requirement date = period end).

But running MRP, the system Cumulates all the monthly requirement from the 2 nd period and creating the order proposal with the order end date of the months first planning calendar week. But I'm expecting the system to create the order proposal with the month's last date as the order end date .

Whether my expectation is incorrect or any other settings to be maintained to achieve this.

Thanks & regards,

Mahesh