on 06-27-2017 12:22 PM
Hi,
I have not been able to create the PR for a leading part grouped under MPN-MRP sets and maintained under FFFC.
FFFC having two materials -> Both maintained under same MPN-MRP set for a specific plant, one of them marked as Leading part -> PIR created for non leading part -> MRP Run for the leading part (as that can not be run for the non-leading part now) -> Stock requirement list for non leading part shows "Available quantity determined for the leading part" -> However the Purchase Requistion for the leading part is not created.
I did it for HERB material type (having same base UOM, Mat type, MRP type, MRP group, Period Indicator) but it didnt work.
I did it for HALB material type too (having same base UOM, Mat type, MRP type, MRP group, Period Indicator) but it didnt work.
Regards.