May 15, 2007 at 05:35 AM

Planned Del Time

59 Views

Client req:

I do not want to maintain Planned Del Time in material master, but in info record.

Quota Arrangement

100 pcs required.

Vendor 1 :60% Pl del Time:10 Days in PIR

Vendor 2 40% Pl Del Time: 30 Days in PIR

MRP run carried out.

How will this material be planned(what will be the date of PR creation) in MRP using quota arrangement.

regards

VS