Automatic assignment in SAP MRS based on demand priority

Jun 29, 2017 at 09:52 AM

72

avatar image

hi

I have maintained priority as very high in the pm orders (demands) for SAP MRS

I notice that , even if i have maintained very high priority , the scheduling is still being done on date basis (first come first serve).

1)I want the automatic scheduler /optimizer to schedule the high priority orders before the others.

2)In case there are already assigned , earlier assignments are to be removed and the high priority ones are to be created

10 |10000 characters needed characters left characters exceeded
Former Member

Hi Dhanashree Savant,

Have you solved?

I have a similar issue.

Regards,

Gavino

0

Hi,

same issue. Do you have a solution?

Best Regards

Christian

0
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Mohammed Yakub Shah
Oct 04, 2017 at 11:00 AM
0

Hi Buddy,

Automatic assignment will work first come first serve if you have activated on save.

Else you will need to use the optimizer and re-schedule all orders again, which will delete existing assignments and create it new.

I would recommend to use optimizer in this case, you can even schedule it on hourly basis if needed.

Thanks and Regards,

Show 1 Share
10 |10000 characters needed characters left characters exceeded

hi,

is there any code change required for this? how to i schedule based on order priority?