Automatic assignment in SAP MRS based on demand priority

hi

I have maintained priority as very high in the pm orders (demands) for SAP MRS

I notice that , even if i have maintained very high priority , the scheduling is still being done on date basis (first come first serve).

1)I want the automatic scheduler /optimizer to schedule the high priority orders before the others.

2)In case there are already assigned , earlier assignments are to be removed and the high priority ones are to be created

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 04, 2017 at 11:00 AM

    Hi Buddy,

    Automatic assignment will work first come first serve if you have activated on save.

    Else you will need to use the optimizer and re-schedule all orders again, which will delete existing assignments and create it new.

    I would recommend to use optimizer in this case, you can even schedule it on hourly basis if needed.

    Thanks and Regards,