SAP MRS: Unable to Assign Work in Non Available Time

Hi,

In MRS planning board the availability is being fetched from the PWS (planned working time- infotype 007). And it is showing the resources as available in MRS planning board (/MRSS/PLBOSRV). As per the business requirement, there would be instances when the work needs to be assigned to resources in non- working times.

In the planning board profile I have selected the checkbox 'Create Assignment at Dropped Times', and have removed the checkbox for stretched assignments.

When I drag the assignment when resource is unavailable, the system reduces the duration to 0 hrs on save.

Please advice how to handle this.

Regards,

Amit