SAP MRS- Operations of different plants don't appear on planning board

amit_saxena7
Active Participant
0 Kudos

Hi,

I have a scenario where a referral work in involved, which means work center of plant A is working on an order and needs an operation executed by work center of plant B. Original work order was created for plant A.

Order (Plant A)

- Operations

- 0010: Work center of Plant A

- 0020: Work center of Plant B

When I open this order on MRS planning board, only operation 0010 is visible. No authorizations have been set up for MRS yet.

I've compared the operations and everything is setup properly including statuses etc.

1. Is this standard MRS behavior?

2. Is there a setting/ note which can be done to overcome this?

Accepted Solutions (1)

Accepted Solutions (1)

amit_saxena7
Active Participant
0 Kudos

Closing this as the issue is resolved.

For the benefit of those who might encounter this issue, the plant and order type combination needs to be maintained in the following config path-

SAP Multiresource Scheduling> Sources of Demand> PM/CS Orders> Define Resource Planning Relevance for PM/CS Orders (ERP)

Thank you!

amit_saxena7
Active Participant
0 Kudos

Didn't mean to select my own answer as 'best', but closing the question is confusing and i tried all options.