SAP MRS- Operations of different plants don't appear on planning board

Hi,

I have a scenario where a referral work in involved, which means work center of plant A is working on an order and needs an operation executed by work center of plant B. Original work order was created for plant A.

Order (Plant A)

- Operations

- 0010: Work center of Plant A

- 0020: Work center of Plant B

When I open this order on MRS planning board, only operation 0010 is visible. No authorizations have been set up for MRS yet.

I've compared the operations and everything is setup properly including statuses etc.

1. Is this standard MRS behavior?

2. Is there a setting/ note which can be done to overcome this?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jun 28, 2017 at 07:06 PM

    Closing this as the issue is resolved.

    For the benefit of those who might encounter this issue, the plant and order type combination needs to be maintained in the following config path-

    SAP Multiresource Scheduling> Sources of Demand> PM/CS Orders> Define Resource Planning Relevance for PM/CS Orders (ERP)

    Thank you!

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Didn't mean to select my own answer as 'best', but closing the question is confusing and i tried all options.