on 06-28-2017 11:25 AM
Dear ALL,
I have created PO with delivery date 15 july. I want to keep tolerance for delivery date as 5 days. Means between 10 july to 20 july on MIGO should be allowed. Remaining dates system should give error for MIGO.
Please suggest standard customization.
Hi Mangesh,
I believe for this you need to take the help of development team. But if you want't to put some date beyond that the GR will not be allowed then you can use "Latest GR Date" . Hope it helps.
Regards,
Arun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As per my knowledge,GR tolerance limits can be set based on the quantity only .It is configuration settings .
Not done anything to restrict based on past due date. If you have to try this requirement then may be you need to write custom code in a suitable
exit/badi during GR .
Regards,
Avik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.