CTM is planning excess production

<u>Background:</u>

We are implementing APO-CTM functionality for a biotech / pharma client. The Bills of materials are very deep and we have fixed lot size quantities at several levels in the bills of materials. We are currently using infinite mode planning in CTM

<u>Problem</u>

CTM is building excess supplies in summary. The number of planned orders generated are very high. We are really not sure what is going on and am thinking some of you may have encountered these issues. Any advice on this problem will be of great help.

Thanks,

Pavan K Vankadaru

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 14, 2007 at 04:25 AM

    There are many factors which might cause over production.

    One of the factors which I can think of

    -- Safety Stock setting

    Regards

    Kumar