on 05-12-2007 3:10 PM
Dear All,
while releasing the production order 0 inspection lot created.
I assigned the inspection plan to all material.
please guide me.
Rgeds,
Vijay Mankar
Hi,
I have had the same problem with all material master data OK.
When you release a production order, the system uses the date of routing transfert (usually same as the date of BOM explosion) to read the QM data.
If the routing has been deleted between the moment your read the PP informations and the moment you release the order, QM data does not exist any more and the inspection lot can not be created.
The only way is to read PP master data just before releasing the order, to be sure to use up-to-date data.
Regards,
Lionel Pons
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
check in the opl8 transaction whether inspn type has
been assigned
check whether qm proc is active in qm view of material
master and qm control key is assigned in the material
master
check whether inspn setup has been carried out
check whether inspn plan has been created with usuage
5 and status 4
check whether in the op control key in the inspn plan
for the work center whether inspn charac reqd ind is
active.(pp06)
If the inspn data has been maintained in the qm view
of the material master then the system has to create
inspn lot automatically as soon as first op is
released .
If the inspn lot could not be created the system has
to set the status ILNC
Regards
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.