Shift scheduling in SNP Run

We are trying to use APO for Shop Floor Planning.

I want to know, can SAP - APO (Optimizer Run) give shiftwise planning instead of day bucket ? i.e. instead of daily requirement, 3 shifts requirement saperately ?

Thanks in advance.

Rajan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 14, 2007 at 11:02 AM

    Hi Rajan,

    SNP is bucketed planning and the most granular bucket is a DAY.

    So in SNP you cannot do shiftwise planning. You need to use PPDS for shiftwise planning.

    Thanks,

    Somnath