Hi all,

I am trying to transfer the demand from APO to ECC, have done the following steps.

1. Cretaed active integration models for that product / location.

2. Had publication type "Planned Independent Requirement: for the location.

3. Have cretaed Transfer profiles and scheduled as background job.

Then i got the following error message in CIF when i transfer the demand from APO to ECC.

<b>10.05.2007 Planned Independent Requirement (Inbound) 3 Source system:</b> hllsap76 user: JAGADEESH transaction: function module: CIF_PIR_INBOUND

<b>10.05.2007 Planned Independent Requirement (Inbound) 2</b> Requirement was already available

<b>10.05.2007 Planned Independent Requirement (Inbound) 1</b> Requirement blocked

<b>10.05.2007 Planned Independent Requirement (Inbound) 3</b> BRBF111 INDH

When i see the details of the error message , it gives the following message:

<b>Error when calling function module

CIF_COCKPIT_START_TRANSACTION: Error code

ThControl: illegal sap_dext call !!! / con</b>

Please guide me, if i miss any settings.

Thanks in advace,

Regards,

Jagadeesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If you are using an R/3 Kernel release of less than 6.20 check out SAP OSS Note 435815.

Regards

Ian

Former Member
0 Kudos

Hi Ian,

Our R/3 kernal release version is 6.40.

Please let me know if any settings i have missed out.

Thanks & Regards,

Jagadeesh.