on 05-10-2007 10:52 AM
Hi,
I would like to create Milestone in ECC 6 from Cprojects. Iam using Multi level controlling using WBS elements with task based Accounting Integration.
Best Regards,
Joseph.
<Post was moderated>
yes... multi level controlling
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I do agree that Task in the Cprojects are created as WBS elements in Multi Level Controlling. But can the automatic transfer from task to WBS element, happen with milestones for WBS elements...
Is there any standard way of creating WBS Element Milestone during automatic transfer of Cprojects Task to WBS element in ECC 6.0 system.
Best Regards,
Joseph.
<Post was moderated>
hi joseph,
do i understand it correctly? you want to create a milestone in PS using MLC?
i think this is not possible. MLC only creates WBS elements.
br, thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.