Hi,

I would like to create Milestone in ECC 6 from Cprojects. Iam using Multi level controlling using WBS elements with task based Accounting Integration.

Best Regards,

Joseph.

<Post was moderated>

Accepted Solutions (1)

Accepted Solutions (1)

schneidertho
Advisor
Advisor
0 Kudos

yes... multi level controlling

Former Member
0 Kudos

I do agree that Task in the Cprojects are created as WBS elements in Multi Level Controlling. But can the automatic transfer from task to WBS element, happen with milestones for WBS elements...

Is there any standard way of creating WBS Element Milestone during automatic transfer of Cprojects Task to WBS element in ECC 6.0 system.

Best Regards,

Joseph.

<Post was moderated>

Answers (1)

Answers (1)

schneidertho
Advisor
Advisor
0 Kudos

hi joseph,

do i understand it correctly? you want to create a milestone in PS using MLC?

i think this is not possible. MLC only creates WBS elements.

br, thorsten

Former Member
0 Kudos

Thank you for the reply...

But what do you mean by MCL? Multi Level Controlling ???

Please clarify.

Best Regards,

Joseph