05-09-2007 3:51 PM
I check the MRP view of a material via MD04 and see a production order or a planned order for a material if I follow "pegged requirement" button I end up with the customer order that causes this production order or planned order.
How the system related the production (or planned order) with the definite customer order ?
Is it stored on a table or calculated on the fly ?
regards.
erk.
05-09-2007 3:57 PM
05-09-2007 3:57 PM
When customer give order and then it creates sales order.
depends on material - I mean Finshed good or Comapny own product ,
If it is outside material ,it creates Purchase req and then Purchase order.
if it is company material ,it creates Planned order and then production order.
Check the transaction you will get better idea.
MD04
MD02
MDBT
LS24
LS26
MMBE
CO01
CO02
CO03
CS03
ME51N
ME52N
ME21N
ME22N
VA01
VA02
VA03
Reward Points if it is helpful
Thanks
Seshu