Changes in PIRs

Former Member
0 Kudos

Hi,

Kindly let know of until which point in the planning process can PIRs be changed. Consider that PIRs had been entered thru MD61, MRP run and Planned Orders generated. How r changes to the PIRs be taken into effect then? If a planned order has been converted to a production order and now if a change is required in the PIRs entered how can this be effected? Will the system take the changes to the PIRs into consideration even after a production order has been generated corresponding to it?

thanks in advance,

Deepak

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

the change in the PIR's will have an effect when the MRP is run. A seperate planned order will be generated if a PIR is increased after the planned order is converted into a production order. If the PIR is decreased, then the next months planned orders are decreased accordingly.All this will happen only when a MRP is run again after the PIR's are changed.

reward points if clear

Chandra

Former Member
0 Kudos

so the system will accept any changes to the PIRs even after a prd. order has been created for it, isnt it?? Is there a limiting point to when the system will accept the changes? does the planning time fence have any effect in this regard?

Thanks & regards,

Deepak