How use Sampling-drawing procedure in different operation in inspection Plan

Former Member
0 Kudos

Dear All ,

i have a Scenario :

  1. i've already created : - Sampling -drawing procedure (QPV2)

- Sampling scheme (QDP1)

- Sampling procedure (QDV1)

2. I've created an Inspection Plan and i putted the Sampling-drawing procedure (QPV2) in the header details. The inspection plan has 2 different operation .

3. Both Operation have inspection charateristic associated to a

Sampling procedure (QDV1) .

4. When i go in transiction QE51N i see for example 3 sample for operation 1 with related inspections dictated by the procedure and 3 sample for operation 2 with other inspections dictated by the sampling procedure of the charateristic in operation 2 .

my question is : Can i have a different generation of samples for each operation or is this impossible because the sampling drawing procedure in the header work for all operation? is there a way to use different sampling drawing procedure for different samples?

For example how can i create automatically 3 samples for operation 1 and only 1 samples for operation 2?

Accepted Solutions (0)

Answers (1)

Answers (1)

krishna_chandra5
Active Contributor
0 Kudos

Hi Francesco,

This is possible in standard SAP. I hope you have created 2 SDP items for 2 operations. In the first item which you are assigning to first operation make the fixed number as 3 and for the item which you are assigning to second operation make fixed number as 2.

System will then create 3 samples for first operation and 2 samples for second operation.

Regards,

Krishna Medasani