Handling multiple units of Same Finished Product

Jun 23, 2017 at 04:51 AM

55

avatar image

Hi Experts,

Our finished product is a bottle, We keep 20 bottles into a Box. This Box will have a separate Label to track.

Need some suggestions to handle this situation.

1) Should we create another Production Order to put these 20 bottles in a Box

2) Should we have a separate operation for keeping 20 bottles in a box in the Original Production Order for the Bottle

3) Do we have any other approach to handle this situation.

Appreciate your valuable suggestions for above queries.

Thanks in advance for your support.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Aditya S Jun 23, 2017 at 10:16 AM
0

Thanks Swapnil for your suggestions.

@ Experts, Can i have some more suggestions to my above queries.

Thanks in advance.

Share
10 |10000 characters needed characters left characters exceeded
swapnil rajane Jun 23, 2017 at 07:20 AM
0

Hello Aditya,

1. First think You need to define alternate Unit of measure for FG material code in material master--> additional data--->Unit of measure tab.So as and when you want to see the stock it will show in both unit in MMBE e.g EA and BOX.

2.Second think if you want separate information related to packing process of the bottles in system then you need configured another order type for reporting purpose if your material code is different for Packed and without packed bottles.

3.Third if the material code is same for both packed and non packed bottles then you can configured 1 order with heading of production process and packing with 2 operations in routing i.e 1st production operation and 2nd is Packing operation.

Regards.

Swapnil Rajane