Creating backend contract

Hi all,

I'm using SRM 4.0 with R/3 backend 4.7. To create the follow-on documents i've activated Extended Classic Scenario (SRM Server - Cross-Application Basic Settings - Activate Extended Classic Scenario). In Org. plan in the tab Function for the pur. organization and pur. group I checked the corresponding indicators but left the Backend Purchasing Group and Purchasing Organization empty. This was done because if I fill the backend pur. group and pur. organization I can't create shopping cart.

After creating the shopping cart I'm creating the Purchase Contract and trying to transfer it to backend. In backend in transaction BD87 there is the following error: Enter PurOrg. Does anybody know what's the problem?

Best regards,

Vlad

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 03, 2007 at 02:33 PM

    Hi Vlad

    Keep the current P.org & P.grp in PPOMA_BBP as they are.

    In PPOMA_BBP, you can create an additional node for backend P.org (in function assign to backend P.org) and then create backend P.grp under this node.

    Would suggest you to use backend p.org and P.grp in contract.

    Best regards

    Ramki