Dear all,
I have set up a work order with two operations with each 1 h work.
Basic start = today; Basic end = 2 weeks from now; Forwards in time and not adjusting basic dates on scheduling.
After scheduling the scheduled start is now and the scheduled finish is 2 h from now. As expected.
When I enter a relationship FS between 0010 and 0020 (without a time interval) and schedule again, the scheduled finish is set based on the latest finish of the last operation (= basic end date, 2 weeks from now)
Also when I enter a time interval it will set the scheduled finish based on the latest finish date of the last operation.
I was expecting that SAP would put the earliest finish date in the scheduled finish date based on the Forward in time scheduling. That should not change based on a relationship.
Can anyone explain this behavior?
Regards,
Robert
Hi all, I have the same issue, in a work order after a relationship, the CM33 shows the scheduling starting from latest dates (it becomes backward) even it is forward at header level.
can you support me please?
thanks
BR
M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Peter,
The problem is that the relationship is messing up my forward scheduling. Even a simple FS relationship between the 2 operations will give me the latest finish date back instead of the earliest finish date.
Regards,
Robert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Robert
Have a look at this OSS Note which explains how order scheduling works.
https://launchpad.support.sap.com/#/notes/0000045433
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.