Material flow between two plants

former_member385587
Participant
0 Kudos

Dear Experts,

We have one process where a material flow through the workcenter operation 1,2,3 in the same plant X and then moves to a centralized operation 4 in another plant Y and again continue back with the same plant X for remaining operation 5,6 and 7. How to define this in a routing. Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Crazy,

1.First you need to extend the material code from Plant X to plant Y.

2.In Plant X maintain external processing control key for operation 4 in routing or order , so once you release the order it will create service purchase requisition.Convert this PR to PO and then do the GR once the operation is complete and material is receipt.Once you do GR your operation status will automatically change

3.In Y plant configured new production order type for performing the production process for operation 4.

Regards.

Swapnil Rajane

Answers (2)

Answers (2)

former_member385587
Participant
0 Kudos

Thanks Almeida. This is fine if the company code is same . If the company code and controlling area is different we need to send it through a PO? In that case we need to have a intra material code ?

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You can have routing operations being executed in a different plant.

Regards,

Caetano