Haie ,

I'm Akma from Malaysia. Actually I need your help regarding the COPC . I have a problem to do Price Update (txn : CK24).

The scenario is my material devide by 2 valuation type (inhouse and external). B4 this I can do the price update using CK24. During the testing, suddenly I delete the future price in costing view (Material Master) using CKR1 (Reorganization of Cost Estimates) . After that, I do the costing run (CK11N) and save succesfully. When I do price marking (CK24), the system didn't give any error but the system prompt information message that "Of 0 materials, 0 cost estimates wer" (message number : CK 705) . Therefore I couldn't release the new price.

Appreciate that you can advice me. Thank you very much.