Cost center change in the Asset master record

Former Member
0 Kudos

Hi

When ever cost center changed in the Asset master record, can it possible what ever the dep that is posted to previous cost center,that will automatically transfers to the new cost center,is there any programme for this,i can use repost functionality in controlling,some time many copst centers changes will happen in

our system,so can any tell me how to automate this.

Thanks

Lily

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Automatic transfer to new cost center is not possible.

You need to use Distribution or assessment to re allocate the expenses to new cost center.

Regards,

Murali

If it is useful, award points