Hi All,

Client has two storage locations- 1000 (Inside the plant premises) and 2000(outside the plant premises).

If there is not a sufficient space in SLOC 1000, the client instructs the vendor to deliver goods at SLOC 2000.

When it is required to bring the goods from SLOC 2000 inside the plant premises, the client makes arrangement of transporter.

The transporter is paid the freight.

How to map this scenario ?

How to book this additional cost of freight into stock account of that material?