Skip to Content
avatar image
Former Member

pm order dates

I need help on SAP PM work order dates both in headers and in operations i.e basic start, basic finish, schedule start, schedule finish, Actual start, Actual finish and in operations Earliest start, Earliest finish, Latest start, latest finish, Actual start, Actual finish.i was read so many document but exactly with example no one given.kindly any expert give ans with an example.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jun 21, 2017 at 06:41 AM

    Have a look at this OSS Note hich explains how order scheduling works.

    https://launchpad.support.sap.com/#/notes/0000045433

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 21, 2017 at 05:39 PM

    Hi Peter,

    Thanks for reply

    i have not any s-id,kindly send me the note.my mail id-manasghosh.sap@gmail.com

    Regards

    Manas

    Add comment
    10|10000 characters needed characters exceeded