on 04-25-2007 6:50 AM
Hi,
How can make components availabilty check after changing the planned order without running MRP please?
Thanks!
Hello Mandy,
If you change the planned order then also you can check the availability of the components from MDVP transaction.
Regards
TAJUDDIN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mandy,
You can use the transaction co09.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
when u go to the change mode of the planned order, u have the ATP check pushbutton. Is that what u r looking for ? If u change the planned order also, it will show the result, though MRP is not run.
Please Reward if useful
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mandy,
Go to COR2(Incade of PP PI) or CO02(Incase of discrete),click 'materials' on application tool bar or you can use following path.Process order(Prodction order)-----function--
availibility check.
Regards,
Shailendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.