Hi All,

i'm trying to copy Actual To Plan using KP98 transaction.

I get the message "Primary cost element ###### is not supported in secondary cost planning". There is no long text to go along with this error message to explain what it really means. I am not trying to do any "secondary cost planning", I am trying to do "primary cost planning" on these primary cost elements. Any idea why the system seems to be trying to do something it is not intended to do?

Thanks,

Rau

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

When you are trying to copy Actual cost to Plan costs, there are default setting to copy all types of actual costs incurred.

You need to click on the "Selection" and remove the tick on Secondary costs if you dont require it. Select "Select Actual Data" instead of "All Actual Data".

Regards

Suraj