BOM replication from ECC to CRM

Hi , recently we refreshed the system from production to quality.

After client copy ,Existing BOM's are not replicating from ECC to CRM . If I change quantity for child material , those are not replicating into CRM. But empty BDOC is generating.

If I create a new BOM , then it is replicating perfectly . Even If I change the quantity for child component , BDOC generating with data in CRM .

I am not understanding what is the issue exactly. I checked all middleware setting those are fine .

Please help me in this.

thanks

rama

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jun 22, 2017 at 06:08 AM

    Hi Ram,

    This is probably issue with the LOGSYS value present in master data and BOM set type tables. When you create a new BOM, the logsys of new ERP system would be used and any delta change in BOM would get replicated successfully. The existing BOM would have logsys that refers to that of production system and since you have copied it (and probably changed the logsys value for the system), it sees a difference and hence ignore the changes.

    Regards,

    Athreya

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 06, 2017 at 03:22 AM

    Raised OSS message one the same issue.

    2505343 - Issue BOM replication from ECC to CRM