cancel
Showing results for 
Search instead for 
Did you mean: 

Kanban Replenishment

Former Member
0 Kudos

Hi Everyone,

We have a Kanban-WM scenario.

We have defined status sequence as Wait-Empty-Full.

When I'm doing the container Empty from Full in that case there is no problem ans also from doing Empty to Wait there is no problem.

But while doing Kanban replenishment through PKBC from Empty to Full we are getting "Update was terminated" message.

Its urgent , please advice.

Thanks a lot.

Mayur

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member196398
Active Contributor
0 Kudos

Hi Mayur,

Please check and analyse the update termination error details in "SM13" transaction. It could be some number range problem or some other validation is failing.

Hope this is useful,

Regards,

Prasobh

Former Member
0 Kudos

Hi Prasobh,

I checked SM13 but I only got the Function Module in which I'm getting the error.

Then I checked SE37 for that Function module. But this is also not very informative.

Actually what is happening when we reverse any activity after that I'm getting an termination massage.

For ex.

Say I have a material "A" and I convert it to Empty from Full then I get one planned order.

And when I reverse it the palnned order gets deleted and the status changes to again Full.

And after that when I'm again trying to make it Empty in that case I'm getting an termination message.

Regards

Mayur