Skip to Content
0
Apr 24, 2007 at 08:36 AM

PPOME - Can't insert the SAME task for different organization unit

114 Views

Hi all,

I have a doubt; in SAP 46C, it seems that is impossible to insert in PPOME, Detailed window, Tasks tab the same task for different organization unit. The only way to do this is in PP01 - General management, where you can explicitely create a [B-007] relations with the same "T" Object. Now, it is a little bit difficult for a user to switch from PPOME ad PP01 when defining new organizational structure.

The question: is there any way to insert the <b>SAME</b> task directly in PPOME, overwriting the standard behaviour of the system that by default create a new task for each new insertion?

Thanks all