What causes the Planning time fence to move / extend?

martinstuart
Explorer
0 Kudos

Hi,

hopefully someone can help with a question! As background my Plant Calendar is 7 days and there are no holidays planned. I have a situation where a user has spotted a situation, he has just reduced the planned delivery time from 4 days to 2 days for a Material in the Material, the Planning time Fence is set to 2 days in the Material but when I look at MD04 the PTF appears 6 days away (e.g. today 20th, PTF is 26th. To me this is strange as I believe the change in delivery time is a red herring (not related). The PFT is 2 days so it should sit at 22nd in MD04 - 2 days from today (20th). There are firm Purch Ords sitting at 22nd & 23rd, nothing is happening on 24th or 25th.

Is this system confused somehow by this master data change?

Many thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

If you are using a planning calendar or periodic lot sizing, the planning time fence should cover the entire period.

Regards,

Caetano

martinstuart
Explorer
0 Kudos

Hi Caetano,

thank you for your answer, I understand the Planning calendar impact I believe, the PTF would extend to the next delivery day/date according to the calendar, but I do not understand the Periodic Lot Size can you please explain a little?

Much appreciated