Hi,

I am working in a MTO scenario. the customer here is going to give the delivery date of the finished material.

from that delivery date i should plan my production and purchasing dates.

when i run MRP, system given purchasing and production times & dates

but my problem here is how system is going to consider the times maintained in the sales i.e. pick/pack time loading time and transit time.

can anybody help me solving this issue.

with regards