Dear Experts,

Following is our scenario and requirement.

we have a Parent Jobchain ( JC_Parent) and a 3 chield job chain.

JC_Parent has a wait event.

If the wait event is not raised for 5 mins after schedule , then JC_Parent needs to be skipped/ignored and then next jobs in schedule should continue.

If you have any idea on this , please share.

Thanks,
Ruban.S

cps | bpa
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

G.M. Blom Jun 23, 2017 at 12:04 PM
1

You can put a time window with overdue after 5 minutes to cancel the chain with the event on it