I have the following problem: A PR (purchase requisition) was created, 29 line items were required, 22 got created the first day and the PR was put on Hold to continue on the next day. The next day, the rest 7 items were created and the PR was saved. The thing is that the Workflow item notification was sent only for the 7 items created on the second day but the other 22 items created the day before remain as 'Wait for status change' and have been there even when the PR has been unheld.

The question here is what event whould make these items to be processed and continue with the Workflow?

Thanks in advance,

Bernal

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Aditya Varrier Jun 21, 2017 at 07:30 AM
0

Hi Bernal,

Not sure why this happened, but what is the BOR you using, is it BUS2105 or BUS2009?

Try to restart the WF from GOS, go to ME52n open the PR, then click the GOS which you find on top left. Click WF>Restart WF.

Hope it helps,

Aditya V