on 04-19-2007 8:49 PM
Hi gurus
I have started a delta load in Quality server
it still running as much of time its take nearly 14hrs for just 60 records
I saw the details tab and it shows the Extraction in yellow and remaining all are in green i mean Transfer , Processing , Subsequent processing , ODS Actication all shown in green
Can some budy give advise
Thanks
KGB
Hi KGB,
Any reason why you chose not to terminate this job. And as Diego suggested, do check the dumps and also sm37 (i think) to see if you have a lot of resources tied up for other jobs that are running. Either way, 14 hours is too long for 60 records, isnt it ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi KGB,
Check in the source system if you have any process running. I think that it may have occurred an error in souce system and BW wasn't notified.
Check for dumps in R/3, using transaction ST22.
Hope this helps.
Regards,
Diego.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.