on 06-19-2017 2:31 PM
Hello Friends,
I am having scenario wherein production order created account assigned WBS Elements.
Planned cost for Production Order does not include Material Cost, it captures only Activity Cost. Where as when I confirm Production Order it shows material as well as activity cost.
E.g. Production Order # 10800022
Plan Costs Act. Costs
2,250.00 24,540
Plan cost should be:
22,290.00 + 2,250.00= 24,540.00
Castings Purchases = 22,290.00
Internal Activity Allocation 310010006/ASSY01 = 2,250.00
Where as in report it shows only 2,250.00.
This Actual Cost 24,540 includes Material cost, In MRP 2 view Backflush is set as 1.
In configuration OPSV Order Category both 10 and 20 check box is tick marked.
Please let me know if I missed any config here?
Please note, I am working on HANA S4 platform.
Deepak M Pitale
Hello Ken,
I am using Valuated project stock. My all PP orders are account assigned to WBS Elements.
Deepak M Pitale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using Valuated or Non-Valuated Project Stock? And are any pf the materials on the PP order Project Stock?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.