Planning Area initialization

Guys,

I am currently using APO 4.1, and wanting to automate the re-initializing of planning area via background jobs. The intention is to re-initlaize the planning area every month, thereby ensuring the timestream exists from the current month +12 monts (for example). However there are 1 or more key figures that I only need to extend + 6months rather than 12. I relaise there is the option called Maintain Key Figure horizons, but how to you maintain these in a variant that want to dyamically calculate the start and end dates. has anyone done this?

regards

Paul

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 19, 2007 at 09:45 AM

    Hi Paul,

    Can you check the fields P_KEYHO and P_PROCID in the variant attributes for report /SAPAPO/TS_PAREA_INITIALIZE. These are new fields and looks to be relevant for the keyfigure and the time horizon for that.

    I have not tried it out but hope this works.

    Actually looking through the report code and OSS notes to dig further.

    Thanks,

    Somnath

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 20, 2007 at 08:24 AM

    Hello Pual

    Just some remark using key figure specific horizon furing re-initilization.

    This function contain some bugs, so you have better to check following SAP Notes. These notes are related to SCM4.1.

    SAP Notes 993572 / 963312 / 939270

    Best Regards

    Keiji

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Keji,

      thanks, as you were probably replying, I have just found the same OSS notes. the problem I have is that we are on SP13, but some of these notes so not seem to have been applied.

      Cheers

      Paul