Project system bom:MRP run is doubling requirements

45 Views

This is an engineering to order enviroment. Project is created from sales order; multi-level sales order bom is transferred to project network activity in cn33. Once the project is released, mrp is run (md02 or Cnmm). Planned orders are created for the network, but they are also created for the dependent requirements of the parent assembly and sub-assembly nodes in the multilevel bom. I have tried using the setting of 1 in the MRP dependent requirements field on the MRP 4 view of the assembly material numbers, but then no planned orders at all are generated in the mrp run. I think there must be a way to have the planned orders created from the project requirements only and not have them duplicated by the dependent requirements of the parent assemblies.