on 04-18-2007 12:11 PM
hai,
i want to create 10 profit center. can any one guide me in this regard (step by Step). we are using mySAP 6.00 ECC.
govind.
chk these screen shots
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hai,
thanks for the message and i was created dummy profit center and profit center. At the time of making journal entry. i have selected the profit center 2000 but the systems gives error message that proft center was set to Dummy Profit center. Pls guide me how to post the entry in 2000 instead of dummy profit center.
govind.
hai,
i have created two profit center and one dummy profit center. In proft center 1100 have posted one journal entry but the system was taken dummy profit center (i.e PGENERAL) and the following message is displaying
Profit center was set to PGENERAL
Message no. KI339
Diagnosis
You entered profit center P1100 or transferred it from a previous transaction, such as material receipt from an external order. However, the system derived profit center PGENERAL from the account assignments.
System Response
The system automatically determines the profit center from the assigned profitability segment, cost center, order, project, network, sales order, or cost objects. This overrides the profit center you entered manually.
Procedure
To post the data to profit center P1100, assign the profitability segment, cost center or other object to that profit center as well.
If the posting to profit center PGENERAL is correct, no further action is necessary.
This message is sent as an error in the standard system. You can make the message a warning or deactivate it entirely in Customizing. Use the Implementation Guide under "Controlling: General" and choose Change message control. Enter area KI and message number 339.
govind
hai,
Printing & Stationery expenses entered in Proft center P1100 because this expense is relate to this profit center.While making entry all the profit center is showing to select. If i select the particular profit center for save option, it is automatically changed to Dummy profit center and saved.
govind.
Hi
PC is to be assigned to any of the cost objects like cost center, IO etc. If system does not find any assignment , then it automatically selects Dummy PC. Assgin PC to CC in CC master data.
You can check PCA assignments monitor to check out if any PC has missed out assignment ( in 1KE4 )
Hope this helps
Pushkaraj
Message was edited by:
pushkaraj kulkarni
hai,
I can't assign in profit center in Cost center master record. because we have 4 cost center and 9 profit centers. If i assign the cost center 1 to profit center 1 then i can't able to assign the cost center 1 to proft center 2. that is my problem.
cost center 1 will be used all nine proft center
cost center 2 will be used all nine profit center like wise.
that is why i am not assigned the profit center in cost center.
I have checked up 1KE4 PC accounting : Assignment master there is empty screen in that assignment monitor (cost center) which one is i want to maintain in the following
nonassigned
assigned cost center
profit center without cost center
govind
Hi
You have to assign the Profit center in the cost center, Assign one of the profit center after wards you can use assessment in profit center accounting to split the cost to nine profit centers. For the data to flow to the proper profit center an assignment in Cost center is a must, otherwise it only go to the dummy profit center. Or otherwise you can use derivation through 3KEH
Anand
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.