Skip to Content
avatar image
Former Member

PR Delivery Date for Service PR generated from PM WO operations

Hi SMEs,

Hope you are doing great.

For a planned , forward scheduled work order, external service procurement operation’s PR is having delivery date as operation early finish date! I was expecting the PR’s delivery date to be influenced by operation’s early start date. Can you help me where we are going wrong here? Is there any config that can influence PR to pick up it’s delivery date from operation early start date instead of operation early finish date?

I tried exploring OPU7 (Scheduling parameters), but no luck. Badly need your assistance here, can you do some investigation

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jun 15, 2017 at 02:44 PM

    Hi,

    The logic is that a component would be required at the operation start date. In the case of a external operation it is expected that the external work needs to be delivered for the operation end date - so requisition date is set to operation end date. User exit COZF0001 could be used to adjust the delivery date on the PR.



    -Paul

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 16, 2017 at 03:21 AM

    Thank you Paul for your Quick response.

    Regards

    Makarand Gurjar

    Add comment
    10|10000 characters needed characters exceeded