PR Delivery Date for Service PR generated from PM WO operations

Former Member
0 Kudos

Hi SMEs,

Hope you are doing great.

For a planned , forward scheduled work order, external service procurement operation’s PR is having delivery date as operation early finish date! I was expecting the PR’s delivery date to be influenced by operation’s early start date. Can you help me where we are going wrong here? Is there any config that can influence PR to pick up it’s delivery date from operation early start date instead of operation early finish date?

I tried exploring OPU7 (Scheduling parameters), but no luck. Badly need your assistance here, can you do some investigation

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank you Paul for your Quick response.

Regards

Makarand Gurjar

paul_meehan
Advisor
Advisor
0 Kudos

Hi,

The logic is that a component would be required at the operation start date. In the case of a external operation it is expected that the external work needs to be delivered for the operation end date - so requisition date is set to operation end date. User exit COZF0001 could be used to adjust the delivery date on the PR.



-Paul