Can actul GI date differ from planed GI date?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Gopala,

Yes this two dates can be diffrent.

Generally plan planned GI date system populate automatically.

If in any case ur goods issue got delayed u can enter actual GI date manually.

Reward if it hlps....

Former Member
0 Kudos

Hi,

Yes it can differ.Actual GI date is nothing byt the PGI date.If you create delivery today then your planned GI date will be today.And after 2 days you perform PGI then Actual GI date will be automaticaly updated in delivery document after you do PGI.

Reward points if helpful.

Regards,

Amrish Purohit

Former Member
0 Kudos

Planned goods movement date

The date on which the goods must physically leave the shipping point to reach the customer on time.

Actual goods movement date

The posting date for the material document is filled using the actual goods movement date. The document date shown on the material document is the current date.

these 2 dates can differ.