Set Up Time -Scenario

37 Views

Hello Sir,

I am having a routing for my Fert with one operation . Setup and machine

times are 30 minutes(example) and 510 minutes(example) respectively.

Shift timings are from 6.00 am to 14.00 pm ( with out any break - example)

8.00 hrs.My individual capacity is 1.

When i created a prodn order my set up time starts on 12.04.2007 at 1.00 pm

and ends at 1.30 pm .From there my machine time starts at 1.30 pm and

on 12.04.2007 at 14.00 pm shift time ends for the day-No more

available capacity ).Again on 13.04.2007 at 6.00 am i need to setup the

machine for my prodn to go smooth for the whole day and after finishing setup

my usual prodn starts .How to include this scenario in my routing.

Can anybody explain the settings and how to go about.

Thanks,

S.Nandhakumar