on 04-11-2007 6:04 PM
Hello Sir,
I am having a routing for my Fert with one operation . Setup and machine
times are 30 minutes(example) and 510 minutes(example) respectively.
Shift timings are from 6.00 am to 14.00 pm ( with out any break - example)
8.00 hrs.My individual capacity is 1.
When i created a prodn order my set up time starts on 12.04.2007 at 1.00 pm
and ends at 1.30 pm .From there my machine time starts at 1.30 pm and
on 12.04.2007 at 14.00 pm shift time ends for the day-No more
available capacity ).Again on 13.04.2007 at 6.00 am i need to setup the
machine for my prodn to go smooth for the whole day and after finishing setup
my usual prodn starts .How to include this scenario in my routing.
Can anybody explain the settings and how to go about.
Thanks,
S.Nandhakumar
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello tajjuddin,
I got the answer for including my set up time for a particular op daily.
Ans:
In opu3 set the indicator shift order.
confirm the particular op partially at the shift end
for the remaining qtys schedule the op for the next day by entering dates
manually
this will include set up time for next day and process time for the remaining
qts.
EX ;
my set up time for op is 60 mins/Process time is 1min for 1 pc
total available time is 480 minutes(NoBreak)
Scheduling Forward:order qty is 430 pcs
say for ex
op 1 starts at 6.00 am and ends at 7.00 am.( set up time)
Process time starts at 7.00am and ends at 2.00 pm(shift end)
made 420pcs.schedule the op by entering next day with opu3 shift
order indicator.
For the remaining 10 pcs again next day op starts at 6.00 am with set up time
and ends at 7.00 am.
Process time starts at 7.00 am and ends at 7.10 pm ( for 10 pcs).
So i am including the setup time daily.
I think this is correct.
Correct me if i am wrong.
Thanks,
S.Nandhakumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nanda Kumar,
Let us not beat around the bush, SAP R/3 does not support minute or hour scheduling of work center. You need to go for APO - PPDS for this requirement or some major enchancement(Which i dont recommend).
Hope this helps...
I See you have closed most of your questions without rewarding points to useful answers.... Please reward so that you get response for your questions.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nanda,
Set up time and execution times depends on the lot size (base quantity) and it has no effects with availabe capacity. If you have multiple (frequent) setup time then you have create a new formula for the multiple setups.
If helpful rewards your points.
Regards
TAJUDDIN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please think realistically.
Once you set up the machine to produce a certain qty , why do you disturb the settings.
Even if you want to stop the machine for the end of the day the machine normally not to be disturbed.
I find there is deviation form the normal working.
Please let me know the full scenario.
Regards
YMREDDY
Hello Balu,
I didn't understand your question. Set up time will be based on the base quantity defined in the work scheduling. For example for base quantity 100 pieces my set up time (for all operations) is 10 minutes and suppose you get the order of 500 pcs then set up time will be multiplied 10*500= 50 minutes.
If your working with multiple setups (suppose frequest berakdown of machine due to power failure and you need to setup machines every time) then you have to define suitable formula in the work center (standard value key) for set up activity.
I hope this is now clear.
If you have any doubt let me know.
Regards
TAJUDDIN
Hi,
In my company i have to heat the die with electrical heaters for about half an
hour daily for the Zinc can extrusion . With out proper heating i wont get
the desired height.Daily there is an early relay operation in each work center in my company where i have to setup the machine for operation to begin at 6.00 am
This is my scenario
Thanks,
S.Nandhakumar
Message was edited by:
S Nanda Kumar
Hi NandaKumar,
As explained please define the available capacity as 7.5hrs. Please work with your CO consultant to capture the daily 0.5hrs warming up time as overhead cost.
Hope this helps....reward your points,
For FAQ on SDN forum please go through <a href="https://wiki.sdn.sap.com/wiki/x/FgQ">https://wiki.sdn.sap.com/wiki/x/FgQ</a>
Regards,
Prasobh
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.