on 06-13-2017 3:34 PM
Hello Nicholas,
We looked at the archive thread for "Integration of PP with PM". It had very useful and helpful notes...but we saw your response at the end stating we should not populate the PP work center in the Organization tab of the PM equipment. We followed your suggestions on what to do and what not to do. But our issue is still we don't see those requirements in CM01 for the PP work center. This is a requirements for our Production Planning team when they are reviewing capacity requirements for the future. We can see our PM order in CM25 when we review our PP data. Any suggestions. Thanks so much for your time!!