Hi,

While creating date types and date duration we can attach reference objects to them. But where do we see the time zones and the factory calendar settings maintained against a reference object?

Regards,

-Sweta

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sweta,

now I have sent you the translation of my own problem. I hope it will help you.

Regards, André

Former Member
0 Kudos

Hi,

can you tell me the steps for how to set up the time zone for a new reference object. I have to create a new reference object with the time zone specific to one of the partner functions in the order.

Thanks in Advance.

Karan

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sweta

If you want to add company holiday to take in account while calculating End date then config for Factory calendar / Holiday

SAP Implementation Guide> SAP Web Application Server>General Settings-->Maintain calendar

Once u done with config, use FM BUSINESS_DATE_CREATE for End date creation.

I am still finding how to attach the FC to Reference object. If i get will post u again.

hope you able to get your result.

Thanks,

Deven

Do not forget to allocate points.............

Former Member
0 Kudos

Hi Sweta,

I have sent you some selfmade documents in german about a problem I have had in former times. I will translate in English and send it later to you.

Kind regards,

André