APO - Product Master - Assembly Scrap

Is it possible to have time-based assembly scrap in the Product Master?

70% scrap effective until 4/30/07

60% scrap effective from 5/1/07-6/30/07

etc

or is it only possible to have time-based scrap in a PDS?

thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Apr 13, 2007 at 09:09 PM

    Hi Richard - you are correct, time based assembly scrap cannot be maintained in the product master (or material master). Time based scrap can be maintained in a PDS or PPM.

    Andy