How to change FY about Testing Plan - GRC 10 - Process Control

0 Kudos

Hello everybody,

In SAP GRC - Process Control, I planning and test the control effectiveness about a process for FY2016, but I put this in system after audit end date (timeframe 01.05.2016 - 30.04.2017) and the system set FY2017 to this work.

There is a solution/workaround in order to change the FY of audit (from 2017 to 2016).

I don't execute the sign-off yet.

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

rajeshwari_akkamgari
Active Participant
0 Kudos

Hello,

The 'created on' date cannot be changed. It always takes the current /today's date when the plan is created. The timeframe you enter in filter gives you the plans which are planned during that year.

Which means , if you plan an assessment now (in 2017) for timeframe 2016- It will show up in 2017 timeframe only

Thanks