Hi gurus.,

In BOM for LUMF there is no delivery for the main item,then why we keep in schedule line CT relevent for delivery,and in item category TAP also we mention A-delivery related billing

Thanks in advance

Narayana

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Apr 06, 2007 at 04:47 AM

    Hi, in BOM generally we configure the item category we use to represent mainitem is relevent for pricing, and also we make it as delivery related billing, since it is delivery related billing without delivering the item u cannot bill the item.what we do is at the schedule line category we make it as not relevent for availability check and TOR.Since the main item cannot be maintained in inventory, without stock system confirms the quantity, in delivery u can pick the items and do the pgi and then main item will be billed during billing

    Message was edited by:

    kiran vemula

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi.,

      Thanks for your response, Shall we do delivery and PGI for the main item in LUMF,that is item category TAP,If we do delivery for main item in LUMG,will there be any stock deduction from plant.,

      Narayana

  • Apr 06, 2007 at 04:59 AM

    Hi,

    In BoM, LUMF will be maitained to price the mateial at Item level.

    where as to upload these sub items ,main item's item category is fine tuned with structure scope-A.

    PRice will be at item level, under main item.

    where as Billing will be done @ Main item level.

    to make the relevant for del in main item schedule line cat -CT, is just to confirmt he order qtty without availability check at main item level.

    this check will be done only at sub item level.

    *Hope this adds info