Please suggest

  1. Points to be considered while Migrating SAP BPC 7.5 MS version to SAP BPC 10.1 NW Embedded
  2. Best alternative approaches.
  3. Pro and Cons
  4. Steps to migrate SAP BPC 7.5 MS version to SAP BPC 10.1 NW Embedded

Accepted Solutions (1)

Accepted Solutions (1)

former_member186338
Active Contributor
0 Kudos

There is no option to "migrate" SAP BPC 7.5 MS version to SAP BPC 10.1 Embedded. Absolutely different things...

It will be a completely new project may be with some ideas coming from old system...

sivaponnuru
Explorer
0 Kudos

Hi Vadim,

Is there any option to migrate SAP BPC 10.1 MS Version Standard to SAP BPC 11 on BW4HANA Standard? Please suggest

former_member186338
Active Contributor
0 Kudos

sivaponnuru

There is no option! Only for BPC MS 7.5... to NW 7.5 then to NW10 then to NW11

Answers (3)

Answers (3)

purnima_kurumeti
Discoverer
0 Kudos
Hi Vadim, The client earlier was on SAP ECC but BPC remained on MS version. Now Client is thinking of move to S/4 HANA and at the same time they want to move from MS BPC to NW version of BPC and most probably embedded version to reap the benefits of S/4 version. For this reason client wants to understand what kind of efforts would be involved in doing this migration (rather we can now call it reimplementation)
former_member186338
Active Contributor
0 Kudos

Complete redesign from zero 🙂

But still not clear what is the expected benefit of moving to embedded? BPC NW standard will also work fine on S/4 HANA. And embedded model support will be more complex...

former_member186338
Active Contributor
0 Kudos

"Please confirm that this approach is not applicable for NW Embedded version." - yes, I confirm!

The question is - why do you want to move to embedded? What is the business reason?

P.S. Even migration to BPC NW standard is a complex job and can result in a complete redesign if there are complex business calculations.

purnima_kurumeti
Discoverer
0 Kudos
Thanks a lot for confirmation Vadim. We had learnt that when we migrate from MS to NW we first migrate from MS 7.5 to NW 7.5 and then upgrade NW 7.5 to upper versions. Please confirm that this approach is not applicable for NW Embedded version. As you suggested I understand that the data modelling and the platform are complete different in MS 7.5 and 10.1 Embedded, just wanted to be sure that there is no “migrate” mechanism which we can utilize to simply the process. Thanks again for the help.
former_member263919
Discoverer
0 Kudos

Hi Purnima,

We are planning to upgrade and migrate BPC 7.5 MS to BPC 10.1 NW .Can you please share the steps if you did already. It would be really helpful .I don't find any SAP standard documentation for the same.

Thanks,

Regards,

Bala.

former_member186338
Active Contributor
0 Kudos

Do you want to migrate to embedded???