Hi,

We wish to enter container No during process order confirmation through cor6n. We see it in MIGo but we required it in cor6n and this container no should flow to QA32 for QC to know the container No.

Regards,

Sun

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

swapnil rajane Jun 13, 2017 at 09:39 AM
0

Hello,

In MIGO may be you are able to see the container number at the time of GRN for a particular material because of sample drawing procedure assign in material inspection plan.But this is from QM point of view for sample management process.

But in PP if you want to capture the same field at the time of confirmation then either you need to add 1 Z field in COR6N screen layout by using the user exit.

Or if you are using PI sheet then you can add the same field by doing PI sheet configuration.You can search for any one of the options to get more detail information.

Regards.

Swapnil Rajane