Hi,

can someone tell me how to 1,

and 2, create process chains for master data load is it just the smae as creating normal process chains?

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Process chain concept is the same whether it is master or transaction.

But for master data you need to make sure you add the process type change run at the end of the load process.

Ravi Thothadri