Skip to Content
0

Creating PR derectly via MRP failed

Jun 12, 2017 at 01:56 AM

63

avatar image
Former Member

Hello! I have a problem that I need your help!

When i try to creat PR,directly via MRP(in the MRP run ,the MRP control parameters i choose is"1 3 1 2 2")the system shows me the exception message "40".the material's Procurement type is "F".However,I can create planned order and transfer it into PR.

Hope received your reply!

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
Jun 12, 2017 at 08:20 PM
0

Hello

Can you please provide a screenshot of the MRP list?

Regards,

Caetano

Share
10 |10000 characters needed characters left characters exceeded
swapnil rajane Jun 13, 2017 at 11:02 AM
0

Hello,

This error happened in many case, maybe because you've not yet maintained number range for purchase requisition.Please check in configuration of Carry Out Overall Maintenance of Plant Parameters the number range "01" is maintain for purchase requisition.

And also please refer OSS notes 550441 question no 06 for Exp message 40 Coverage not provided by master plan.

Exception message '40' resulted from the calculation of the ATP quantity in Transaction MD04.The calculation of this ATP quantity is not provided anymore in Transaction MD04 since it was not an "actual" ATP quantity as in Transaction CO09, but it was calculated according to a separate logic which did not take into account certain relevant parameters.Branching to the ATP quantities now leads to Transaction CO09 which considers all MRP elements, checking rule and scope of check.This instrument should be used now, here the previous exception message '40' is equivalent to a negative, cumulated ATP quantity.In Transaction MD04 exception messages '10' and '30' from the rescheduling check can also be used to determine receipt elements that are not covered.

Regards.

Swapnil Rajane

Share
10 |10000 characters needed characters left characters exceeded